ENTERPRISE TAB WATCH

Results

November 10, 2010

 

Planning Commission 7:00 P.M., Tuesday, December 7, 2010.

Board of County Commissioners 9:00 A.M., Wednesday, December 8, 2010.

 

The PC decisions/recommendations may be appealed to the BCC within five business days of the date of the PC hearing.  Appeal form is found at:

 

 Clark County Appeal Form

 

An appeal may be made in person at the Current Planning desk or by fax (702-455-3271).  Call Current Planning (455-4314) to find out how to file an appeal.  Help in filling an appeal may be obtained from the Southwest Action Network (SWAN).  You can contact SWAN at:

 

702-837-0244 · 702-837-0255 (fax)
email:   swan@lvswan.org

 

Note: If you click on the blue underlined text it will take you to the detailed documents to explain the agenda item.

 

REGULAR BUSINESS

1.Approve the Agenda with any corrections, deletions or changes.  APPROVED

2.Approve the Minutes for the meeting held on October 27, 2010.    APPROVED

3.Discuss and make recommendations as required on AG-0967-10.

 

The TAB continued the discussion with the definition of “commence” and “extension of time” being reviewed.  Currently commence means any of the following:

 

·                     The actual placing of construction materials in their permanent position fastened in a permanent manner,

·                     Basement excavation,

·                     Demolition or removal of an existing building or structure preparatory to rebuilding,

·                     Grading of the site,

·                     The recording of a subdivision map, or

·                     In the case where a building permit or business license is not required, the actual start of an approved use.

 

The following were ideas were put forth:

 

·                     Shorten the time allowed for an extension of time

·                     Better define why the extension of time is required

·                     “Extension of time” is for review, commence a project, and complete a project.

·                     Site grading may not be a good commence point

            Continued until December 1, 2010 meeting

            Approved

 

ANNOUNCEMENTS

1. Clark County Administrative Services is taking applications for TAB Members for 2011-2012.  A hardcopy of the application is required.  Applications are due by 19 Nov 2010.  The application can be found at:

http://www.accessclarkcounty.com/depts/administrative_services/Documents/TAB%20Application%200405.pdf

 

PUBLIC COMMENTS AND DISCUSSION

 

1)         Southwest Gas has learned that individuals posing as Southwest Gas representatives are showing up at residents’ homes asking to check their appliances or home insulation. Although these imposters could be wearing what look to be Southwest Gas uniforms and official-looking identification badges, the company is warning residents that it is not a company practice for employees to perform any unscheduled customer service work orders.

 

Please note that outside of special circumstances, Southwest Gas Customer Service and Construction employees:

·      Generally come to a home only when service is requested by the customer;

·      Should enter the home only at the customer’s request;

·      Always drive a marked company vehicle; and

·      Wear a company uniform with the Southwest Gas name and logo visibly displayed, as well as an identification badge that includes the company logo, employee name, and picture.

 

2)         A resident noted that the stop sign requested in the Enterprise capital budget at Warm Springs and Lindell has been installed.  Commissioner Sisolak and his liaison were thanked.

 

ZONING AGENDA

         SEE ATTACHMENT A

 

NEXT MEETING DATE

December 1, 2010 6:00p.m.

Enterprise Library

25 E. Shelbourne Avenue @ Las Vegas Blvd. South

ADJOURNMENT:

 

12/07/10 PC

 

1.UC-0506-10 – SOUTH POINT INVESTORS, LLC, ET AL:

APPROVED per Current Planning conditions

 

USE PERMIT for a major training facility (computer training) in conjunction with an existing office complex on a portion of 1.9 acres in a C-P (Office & Professional) Zone.  Generally located on the south side of Warm Springs Road, 340 feet west of Placid Street within Enterprise.  ss/pb/xx

 

2.VS-0500-10 – WOOD, MARY J.:

APPROVED per Staff conditions

 

VACATE AND ABANDON easements of interest to Clark County located between Shelbourne Avenue and Wigwam Avenue, and between Gilespie Street and Rancho Destino Road in an R-E (Rural Estates Residential) (RNP-I) Zone within Enterprise (description on file).  SS/gc/mb

 

12/08/10 BCC

 

3.NZC-0982-04 (ET-0164-10) - HURLEY, STEVEN & DONNA:

HELD by the applicant until December 15 TAB meeting

ZONE CHANGE SECOND EXTENSION OF TIME to reclassify 2.0 acres from R-E (Rural Estates Residential) Zone to C-1 (Local Business) Zone for a plant nursery.

 

USE PERMIT for outside storage for a plant nursery to be located in front of the building.  Generally located on the north side of Gomer Road, 300 feet east of Fort Apache Road within Enterprise (description on file).  sb/pb/xx

 

4.            ZC-0300-06 (ET-0169-10) – BBCME LAND, LLC:

HELD by the applicant until December 1 TAB meeting

 

ZONE CHANGE FIRST EXTENSION OF TIME to reclassify approximately 27.0 acres from R-E (Rural Estates Residential) Zone to R-2 (Medium Density Residential) P-C (Planned Community Overlay) Zone in conjunction with a residential subdivision in the Mountain’s Edge Master Planned Community.  Generally located on the northeast corner of Starr Avenue and Buffalo Drive within Enterprise (description on file).  SB/rk/xx

 

5.            UC-0504-10 – BBCME LAND, LLC:

HELD by the applicant until December 1 TAB meeting

 

USE PERMITS for the following:

 

1) reduced front setback to a garage;

2) reduced lot size;

3) increased wall height;

4) allow early grading;

5) reduced street off-set; and

6) modify required street improvements

 

in accordance to the County’s Uniform Standard Drawings in conjunction with a residential development.

 

DESIGN REVIEW for a single family residential development on 95.5 acres in an R-2 (Medium Density Residential) P-C (Planned Community Overlay) Zone in the Mountain’s Edge Master Planned Community.  Generally located between Erie Avenue and Starr Avenue and the east side of Buffalo Drive within Enterprise. SB/rk/xx

 

6.            VS-0505-10 – BBCME LAND, LLC:

HELD by the applicant until December 1 TAB meeting

 

VACATE AND ABANDON easements of interest to Clark County located between Erie Avenue and Starr Avenue, and between Tenaya Way (alignment) and Buffalo Drive, and portions of rights-of-way being Starr Avenue, Buffalo Drive, Boyd Avenue, Siddal Avenue, Chartan Avenue, Monte Cristo Way, and an un-named street located between Erie Avenue and Starr Avenue, and between Tenaya Way (alignment) and Buffalo Drive in an R-2 (Residential Urban Density) P-C (Planned Community Overlay District) Zone in the Mountain’s Edge Master Planned Community within Enterprise (description on file).  SB/rk/xx

 

7.            WS-0508-10 – L V PYLE, LLC:

HELD by the applicant until December 1 TAB meeting

 

WAIVER OF DEVELOPMENT STANDARDS to increase the number of project identification signs.

 

DESIGN REVIEW for a comprehensive lighting and sign package in conjunction with an approved multi-family residential development on 16.4 acres in H-1 (Limited Resort and Apartment) Zone in the MUD-4 Overlay District.  Generally located on the south side of Pyle Avenue and the west side of Haven Street within Enterprise.  SS/mk/xx

 

The statements, opinions and observations expressed in this document are solely those of the author.  The opinions stated in this document are not the official position of any government board, organization or group.  The project descriptions, ordinances board/commission results are reproduced from publicly available Clark County Records. This document may be freely distributed and reproduced as long as the author’s content is not altered.  Additional comments maybe added.  Additional comments must be clearly attributed to the author of those comments and published or reproduced with the document.  The additional comments author’s affiliation with any government board, organization or group must be clearly identified.  This attribution statement must accompany any distribution of this document.

David D. Chestnut, Sr.